Billy Bricks
August 21, 2026
8/18/26
After sawcut and concreted removal, excavated down to new 6" SDR on outside and to old 4" cast iron on inside area 5' deep. Broke out old CI and tunneled under foundation. Stubbed new 6" grease line into building with wye and cleanout. Bedded in stone. Removed concrete and hauled away spoil.
8/19/26
Returned after inspection to backfill in stone over bottom of footing and haul spoil. Removed all inside spoil and hauled away.
Installation on new water heater and expansion tank in River Grove, IL.
Condo Association Parking lot sewer repair. Rebuild storm sewer. Remove 4 parking blocks, saw cut approximately 8 X 8 around storm basin. Breakout asphalt and concrete, and haul away spoil. Install new spacer rings and bricks where needed. Seal inside and outside of basin, install new storm sewer lid and cover. Backfill 100 % stone and compact. Additional work was required. Once excavation started found we had to replace the whole manhole structure wall and some piping 8 inches.
Upon arrival met with Village water works, isolated main to complex. Disassembled water meter, removed flange. Cut out old valve and removed nipple from 4 x 3 bushing. Installed new valve and had village pressurize main. From there installed new 90 and re-tightened flange. Installed water meter fully tightened and pressurized building main. Tested for leaks and flow passed. Cleaned work area.

