Sky Climbers -Skokie, IL

August 26, 2026

Returned to the job site to televise the roof drain from inside the building to the outside manhole. Utilized a lift to cut out the existing leaking 6" roof drain connection and multiple fittings. Removed debris and prepared the area. Re-piped the main 6" PVC and fittings, installed a cleanout, and secured the pipe vertically with support hangers and bracing. Tested the system and cleaned the work area. It's now ready for use.



Hydro jetted from the cleanout of the roof drain towards the side of the building's manhole. Flushed the fixture and conducted tests, which passed. It is ready for use.

November 19, 2026
Installation on new water heater and expansion tank in River Grove, IL.
October 23, 2026
Condo Association Parking lot sewer repair. Rebuild storm sewer. Remove 4 parking blocks, saw cut approximately 8 X 8 around storm basin. Breakout asphalt and concrete, and haul away spoil. Install new spacer rings and bricks where needed. Seal inside and outside of basin, install new storm sewer lid and cover. Backfill 100 % stone and compact. Additional work was required. Once excavation started found we had to replace the whole manhole structure wall and some piping 8 inches.
October 23, 2026
Upon arrival met with Village water works, isolated main to complex. Disassembled water meter, removed flange. Cut out old valve and removed nipple from 4 x 3 bushing. Installed new valve and had village pressurize main. From there installed new 90 and re-tightened flange. Installed water meter fully tightened and pressurized building main. Tested for leaks and flow passed. Cleaned work area.
More Posts